• Ícone Renewable Energy Type of work
    Renewable Energy
  • Cliente Client
    Enel
  • Potência Power
    102 MW
  • Localização Location
    Alta Floresta
    Mato Grosso
  • Period
    2014 / 2016
  • Work carried out in 24 months, in a complex of 3 Power Plants, simultaneously.

    Object: hydroelectric exploitation.

    Description: execution of civil works of earthmoving and concrete, assembly of hydromechanical (gates, coffer, wagon and segment, hoists and grids), civil works of substations, vegetal suppression of reservoirs, rescue of fauna and flora, and recovery of degraded areas of PCH Cabeça de Boi, UHE Salto Apiacás and PCH da Fazenda, located in Apiacás River, between the municipalities of Alta Floresta and Juara, MT, owned by Enel Green Power.

    Apiacás Hydroelectric Complex, with a total installed power of 102 MW – enough energy to supply the needs of more than 200 thousand Brazilian homes and avoid the annual emission of about 280 thousand tons of car-bon dioxide into the atmosphere – was an enormous engineering and logistical challenge, involving and moving huge volumes of land, with autonomous production of concrete.

    Standing out:

    • excavation in soil – 60,000 m³
    • rock excavation – 945,000 m³
    • landfills for cofferdams and dams – 670,000 m³
    • production and pouring of concrete – 220,000 m³
    • application of structural steel and metal inserts – 5,244,000 kg
    • manufacture and application of wooden formwork – 92,000 m²

    Power Plant 1 – UHE Salto Apiacás 45 MW

    Power Plant 2 – PCH Cabeça de Boi 30 MW

    Power Plant 3 – PCH da Fazenda 27 MW

    Gallery

    Click on the map to see the works by State

    Mapa de Obras - Regiões Placeholder
    Mapa de Obras - Regiões

    News

    UFV Verde Vale III, best-performance Photovoltaic Plant in Brazil

    A study made by BEI BRASIL ENERGIA INTELIGENTE classifies the UFV Verde Vale III as the best-performance photovoltaic plant in Brazil (among all 93 UFVs of the CCEE’s report), considering the relationship between the energy generation and installed power since the month following that of the entry into generation of the undertakings. The official reports…

    Read all

    The Environmental Licensing of the Quartéis Complex

    Open to the community, Public Meetings will be conducted by the Superintendência de Projetos Prioritários – SUPPRI.

    Read all

    Drone amplia qualidade das imagens Quebec

    Imagens feitas através de captação por drone, mostra a beleza do projeto PCH Serra das Agulhas, executado pela Quebec.

    Read all
    2021 – All rights reserved – © Quebec Engenharia
    ^